Modalities of Formation
Administrative contracts should be concluded following the formality requirements that the law prescribes. Such a provision is available under the General contracts part of the law. This being the rule, some administrative contracts need additional modalities of formation. Accordingly, we have instances when administrative contracts are concluded following a procedure of tender.
As art 3147(1) makes it clear by utilizing “may be…” it is optional that such a procedure is followed. To show the possibility however the law reads “Administrative contracts (may be) concluded by the procedure of allocation by tender” (emphasis)
Once however we are channeled to make an administrative contract by the procedure of allocation by tender, we will act to the contrary i.e. fail short of allocating by tender, “… under pain of nullity.”
The natural questions will be “Why are we channeled as such And when are we channeled?”
To begin with the second, we are forced to conclude an administrative contract by allocation “… whe never the law imposes such obligation”. Let us consider the full text of Art 3147(2). “(Administrative contracts) shall be concluded by (the procedure of allocation by tender)…, whenever the law imposes such obligation.”
Hence once the law dictates us to conclude an administrative contract by the procedure of allocation by tender we have to do it in that way the consequence of not following the diction being nullity.
Among other things the law prescribes to meet the objectives of transparency and taking into account, the sensitivity of the obligation. Thus tender minimizes potential dealings between administrative officials and the other contracting party. And secondly because after all the contract is to be concluded to provide the best for the public, the procedure of tender aims at selecting the best contracting party in terms of reasonable price and modest quality.
By taking these rationales into account the law prescribes adherence to the procedure with the procedure under Art.3148-3169. To this end, administrative contracts that should be made by the procedure of allocation are governed by Articles 3148-3169.
If the contract is to be concluded after allocation, Art.3148 tells us that “the allocation shall be notified to the public in the manner prescribed by administrative regulations or in default… in the manner which appears the most appropriate”.
The law, in this case, is concerned not only with the publicity issue but even with the mechanism of attaining this publicity. The normal way of publicity is through electronic media and printing media. Sometimes administrative agencies will tell the public through electronic media to read and consider a given series of a newspaper usually to better comprehend with the content of the notice.
The minimum threshold of the content of the notice of allocation is available under Art. 3149 fashioned in a mandatory spirit but effectuates in an optional manner i.e. what happens if the notice fails to include one of the lists under Art.3149?
Though the law is silent on this issue, the publication of those issues under Art.3149 limits the prerogatives of administrative agencies from arbitrarily modifying the specifications. (See Art.3150 cum Art 3149) Mind you specifications can still be modified by a new publication (Art.3150). So, isn’t this tantamount to saying “do not modify the old specification with a new one but only the new with a new one?”
One other issue worth noting is the status of this publication under Art. 3148. Should we consider it as an offer or as a declaration of intention? Note that an offer has a quite different legal consequence from a declaration of intention. See for example Art.1690 and 1687 on this issue.
After administrative agencies declare their intention by notifying the public about the allocation, “The contractors or suppliers who intend to present themselves as tenderers shall deposit in the place indicated and within the time specified by the specifications (a declaration of their intention) to tender and their tender.” (Art.3153).
“The declaration of intention (offer) to tender shall indicate the name, first name, qualifications and address of the candidate.” (Art.3154 (1)]
“The [tender] shall contain an offer of the price and the undertakings of the candidate” [Art. 3155(1)]
Thee above provisions show us the need to comply with formality requirements on the event of declaring our intention. Because they are about declaration of intention, we should not think of the formation of an administrative contract at this level. What else should we consider?
As to Art.3159, for example, “The office of allocations shall firstly take cognizance of the declarations of intention to tender.” To verify whether these have been regularly deposited and whether the tenderer fulfill the conditions required for admission to the allocation. “This verification is not to determine the successful tenderer. Rather it is to determine admission to the allocation”.
A provisional successful tenderer is the one who makes the “most advantageous tender for the administrative authorities (Art 3164 (1). Among other things the most advantageous tender is determined by the offered price. To this end Article 3164(2) reads “for this purpose, the office shall take into account the price offered and all the modalities of the tender in conformity with the specifications”.
Even the designation of a provisional successful tenderer does not imply the conclusion of an administrative contract.
For that matter the office (of allocation) need not designate any provisional successful tenderer where regulations of the allocation prescribe that the administrative authorities do not intend to negotiate beyond a certain price. (Art 3165(1)).
On the advent of approval, the contract shall be concluded. Art. 3168 says the successful tenderer will no more be qualified as a provisional but a permanent successful tenderer.
This being one aspect of forming administrative contracts as governed by the civil code, we have other modalities of forming administrative contracts under proclamation No 430/2005. We will briefly consider the procedures under this proclamation.
1.3.3 Process of Forming Administrative Contracts under the Proclamation
Under private contracts, parties have at every liberty to choose their would be contracting party. This being not the case under administrative contracts the manner of selecting the prospective contracting party will have in view such considerations as ensuring the economic and efficient use of public fund and making public procurement in a manner which is fair, transparent and non discriminatory (Preamble of Proclamation No.430/2005).
Administrative contracts, therefore, have this view in advance thereby limiting contracting parties’ from freely picking up their prospective counter parts.
To begin with our discussion, it is good to first understand what procurement is per proclamation No 430/2005. Accordingly, “procurement” is to be understood as “the purchasing, hiring or obtaining by any other contractual means goods, works and services.” [Art.2 (e) of the proclamation]
We should therefore understand procurement in a wider sense to include not only purchasing but also hiring and any other contractual means enabling the acquisition of goods, works and services.
If this is procurement, what are the means of procurement? The rule here is “open bidding”. That is why Art. 25(1) prescribes “[e]except as otherwise provided in this proclamation, the procuring entity shall [use] open bidding as the preferred procedure of procurement.”
The otherwise provisions of the proclamation are enumerated under Art 25(2) of the same. Next to this, upon delimiting the scope of application of the proclamation, Art.3.(2) takes into account another consideration that authorizes the use of a different procedure of procurement. This is obviously true in purchase of goods, services or works that involves “national security or defense”. But should all procurements that involve the above entities be undertaken following a different procedure than open bidding?
At least six modalities of procurement including open bidding are recognized by the proclamation. These are available under Articles 25-30. They are:
- Open bidding
- Restricted tendering
- Direct procurement
- Request for quotations
- Two-staged bidding.
- Request for proposals.
- Open bidding:
This is the rule under the proclamation. The first thing that comes to mind when thinking of open bidding is advertisement. Art.31 (1) prescribes the modality of advertisement. Thus, “invitation to bid shall be advertised in at least one national newspaper of general circulation. Additionally, the procedures under articles 32-42 should be complied with.
Generally the bidding will be considered as open because it is advertised as such by allowing a great number of bidders to competitively participate. Briefly, there are five steps here:
- Preparation of bid (Art.33)
- Invitation for bid (Art.32)
- Advertisement (Art 31. Cum 35)
- Submission and receipt of bids (Art.37 cum Art 36)
- Opening of bids, examination & evaluation of bids (Arts 38-39)
- 2. Restricted tendering
This is possible after following the conditions under Art 26(1). When “the good, works or services… are available only from a limited number of suppliers” or when the time and cost of bidding is disproportionate to the value of the things to be procured, the mode of procurement will be restricted tendering.
The procedures to be followed under restricted tendering are those listed under open tendering except for the modifications introduced under Art.44.Some of them include:
-
- Invitation to bid is addressed to the few who have already agreed to bid
- Bid security is optional in the sense that it is the procuring entity which determines whether to pose the request or not.
Even though the number of people who participate in the bidding are less than those we already have in open bidding, non-discrimination and fairness are the rules of the game. Procuring entities are expected to render equal treatment to those who participate in the bidding. They should also provide equal opportunity to those in the suppliers list.
- Direct Procurement:-
Generally speaking, the rule in the procurement proclamation is open bidding. However, under clearly enumerated cases direct procurement is envisaged as a possibility. Direct procurement in a way should not be used to avoid possible competition among bidders nor should it be used to discriminate among them. Taking this as background, the proclamation enumerates the possible conditions that warrant the use of direct procurement as one means of procurement. Some of the conditions listed under Art.27 include:
- Absence of competition because of technical reasons,
- Provision of supplies for replacement, as extension for existing supplies or when procurement from another supplier forces the procuring entity to procure equipment or service not meeting requirements of interchangeability
- When additional works which were not included in the initial contract have, through unforeseeable circumstances, become necessary since the separation of the additional works from the initial contract would be difficult for technical and economic reasons
- Determination by the head of the procuring entity that the need is pressing and of emergency and delay will result in serious problem and injurious to the performance of the procuring entity
Do you have anything to say with regard to the list that we have under Art.27? Is the list exhaustive? Why? Why not?
- Details
- Category: Administrative Contract
- Hits: 9509
Validity Requirements
Consent
There is in general no better evidence of the justice of an arrangement than the fact that all persons whose interests are affected by it have freely and with full knowledge consented to it. In the famous maxim of Hobbes ‘‘there is not ordinarily a greater sign of the equal distribution of any thing than that every man is contented with his share”.
Consent is evidential of a right and constitutive of the same. Because of this philosophy therefore we give a paramount place to consent. Short of consent no evidence and no right.
These justifications can be gathered from Art. 1679 and Art. 1680, while the former talks about the constitutive nature of consent, the latter talks about the evidentiary role of the same. Read Art. 3134 and identify the role played by consent. What is the role?
Under Art. 3134, it is the contract concluded by the administrative agencies that proves the existence of consent. Meaning mere conclusion of a contract by an administrative body implies the existence of consent on the part of the administrative body. It partly reads
“…, the conclusion of a contract by the administrative authorities implies an express manifestation of will on their part”
Hence, we derive consent from the specific form that the contract follows. Because Art.1724 prescribes the making of an administrative contract in a written form, this is indicative of the existence of consent on the part of the administrative agencies.
As a formal and not simple agreement the law does not require the mere existence of consent but its manifestation in some particular form.
The law requires therefore proving consent as expressed by the parties. What can be counted as special under administrative contracts however may be the insufficiency of implied consent. Ordinary contracts envisage the possibility of deriving consent from silence under exceptional circumstances. On the part of administrative contacts always one has to prove the existence of express consent. Nowhere therefore silence does amount to acceptance. To be specific, Art.3134 (2) says “Where an authority competent to approve a contract keeps silent, such silence shall not, in the absence of a formal provision, be deemed to amount to approval.”
Capacity
Administrative contracts are made by artificial persons be it the administrative agency or the contractor which is usually a business organization.
Capacity, under such circumstances, means a different thing. It cannot be about a mental state nor can it be about chronology. Rather, capacity is all about establishment, registration or license.
Generally, capacity is either legal or technical. Let us begin with the contractor.
Basically any juridical or physical person that wants to conclude a contract with administrative agencies should have:
- Technical and professional capacity
- Legal capacity
- Financial capacity
D. Fiscal capacity
What about administrative authorities? What capacity should they have?
- The administrative agency should have legal personality which means it should be established through a proclamation or regulation.
- Next to this validity question and after its positive determination the agency should possess the capacity to enter into contracts .Such capacity may emanate from law or practice (i.e. specific activities or functions). Sometimes capacity may also emanate from authorization. Authorization might be a single venture or still a sort of double standard effectuated in a cumulative modicum with other prerequisites.
- An administrative agency is still duty bound to assert its financial capacity. To this end “procuring entities shall be responsible for certifying the availability of funds to support the procurement activity before signing a contract “(Art.7(1) (e) of Proclamation No.430/2005)
Here it is worth raising two questions. The first is, “Does lack of credit have a consequence of invalidating administrative contract?” the second is Can such an act be counted as ultra vies?
To address these questions, it is good to consider articles 3142 & 401 of the civil code and Art.7 (1) (c) of the proclamation. In a crystal clear phraseology, Art. 3142 validates an administrative contract formulated regardless of credit requirement. To be specific, a contract concluded by an administrative authority shall be valid notwithstanding that such authority has not received the necessary credits for the performance of the contract. On the other hand, Art. 401(1) tries to expose what an ultra vires constitutes. Thus, Acts performed by the bodies referred to in this chapter are in excess of the powers given to them by law or without the absence of the conditions or formalities required by law shall be of no effect.
Art 401 serves at least two purposes. Firstly it tries to tell us what ultra vires activities are. Next to this, it sanctions the activities by declaring them as nearly void.
At other times consent might not be this. Rather consent might be approval (Art. 3144) where by no consent is expected to be expressed until and unless “…such approval is given.
This is usually the case “where the conclusion of the contract is subjected to the necessity of a further approval…”
Object
The object of a valid contract should be lawful and possible next to being defined (determined). Art 1711 leaves the parties to freely determine the object of their contracts the extent of the freedom however being “the restrictions and prohibitions as are provided by law.”
You can therefore infer from this that both parties involved in a contract have a say on the object of the contract. Art.1711 thus underscores the fact that object determination is not one way traffic. Peculiar however to administrative contracts, administrative agencies are entitled to formulate in advance model specification, general clauses and common directives (Art 3135) .Predominantly administrative contracts have objects determined by administrative agencies.
However, it is good to note the fact that the legal limit under Art. 1716 is applicable to objects determined by administrative contracts. Can you justify this assertion?
Next to insuring the participation of parties in determining the object of their contracts, the law also wants to maintain the integrity of the object on the face of the law. Though determined by anyone, still the object should be clearly stated in an understandable manner (Art.1714).
An administrative contract should also have a possible and lawful object. To a very large extent parties are free to agree together upon any matter as they please. Limitations are however there-party in the interests of parties and partly on behalf of the public. There are instances where the law admits of no abatement and many in which it will admit of no addition by way of agreement.
Form
Under normal circumstances, compliance to formality requirements is not necessary. (Art.1678(c))
Nevertheless, under those circumstances where the law prescribes, any one has to comply with the prescription. One instance of form prescribed by the law relates to any contract binding the Government or a public administration” under Art.1724)
The requirements of the law here are two. The contract should be made in writing and it should be registered. We can explain of the two fold purposes of the law.
- Designed as a pre-appointed evidence of the fact of consent and of its forms to the intent that this method of defining rights and liabilities may be provided with the safeguards of permanence, Certainty and publicity. Because a contract is law (Art.1731) and because some of the features of a good law with an “ internal morality” per Lon Fuller are permanence, determinacy and publicity writing down a contract caters” the law” these qualities. The quality of publicity conferred on contracts by following Art. 1724 does also serve the ends of Art12 of the FDRE constitution by manifesting the transparency theory.
Any necessary formality has the effect of drawing a sharp line between the preliminary negotiations and the actual agreement and so prevents the parties from drifting by inadvertence into unconsidered consent. What is there in the document expresses the consent. One cannot later modify the consent as written by the one expressed orally.
On top of the prescription under Art 1724, some administrative contracts should be formed following procedures of tender. This will be discussed in depth in our consequent discussion of “modalities of formation.”
- Details
- Category: Administrative Contract
- Hits: 9062
Formation of Administrative Contracts
Legally the life of a contract begins at its formation after parties have consented to be bound by it, if parties have the capacity to legally express their consent and if the object of their contract is succinctly defined, plausible and lawful. [Art. 1678]
Short of this, the law either declares the contracts void or puts the possibility of voidability as the case may be.
Normally the requirements under Art. 1678 are those which determine the viability of any contract. Under this very normal condition, exceptional situations are envisaged with regard to formality requirements. In addition to consent and object requirements, the law also shows the possibility of agreeing in favor of a given form or a form by the normal operations of the law [art.1678 (a) and Art. 1719 by virtue of Art. 1676]. Thus, the law either prescribes adherence to a certain form (Arts. 1724 & 1725), or parties may agree to make their contracts in a written form. Art.1724 makes mandatory that contracts with administrative authorities be made following a written form. Any contract to which a government agency is a party, including any type of employment contract, should be made in writing. In public administration, officials do not stay in office indefinitely rather they may leave their office by election, removal or resignation. Once they leave their office it is difficult to ascertain the content of the contract entered into during their stay in office but that continues to be effective even after they leave their office. Moreover, oral contract opens a room for corruption since keeping information is difficult.
As was noted before, Art. 1676 warrants the use of Title XII on contracts in General by explicitly stating “… regardless of the nature thereof and the parties there to.” Because of this, Art. 1678 and consequent provisions that govern the formation of a valid contract will also be valuable in our consideration. In addition, Articles 3140-3145 and 3134-3136 will be considered. By presuming that you have made an intelligible discussion on the General contracts aspect of the law, our concentration will be on the special part of the law that governs administrative contracts proper. Let us consider the validity requirements.
- Details
- Category: Administrative Contract
- Hits: 24375
Administrative Contracts and Other Forms of Contracts: General Overview
Because of the need to carry out its functions, government, via its branches, will embark upon different activities which inevitably will invite the interplay of its branches and the private sector. These branches other wise known as administrative agencies assist government to properly take its tasks of service provision among other things. It is therefore while these agencies carry out their functions that they use the law of administrative contracts to their ends. The ends are public services, the means administrative contracts.
If this is so, administrative contracts are contracts under the strict sense of the law but only an” administrative” one (see for example Art. 1676(2) cum Art.1675 of Ethiopian civil code with Art.3131 of the same).
But this nature of the contract i.e. being an administrative contract makes the same different from the beginning to the end from other types of contracts that we know.
Our inquiry therefore will be what is there in administrative contracts? What grain of difference does the qualification administrative add over non-qualified contracts?
One basic addition by the qualification is associated with prerogative matters. Because administrative agencies favorably enjoy the presumption of acting on behalf of the public and because public interest is overriding enough to put aside even basic principles of the law the agencies will enter into an arrangement where the platform is squarely fitted to their play than to the other contracting party.
When talking about administrative contracts, hence, one is talking about a contract where the two parties are unequal. Being a contract between unequal parties from the onset, at the end of the day, it will end up entitling parties in unequal manner.
If this is so, how should we define administrative contracts? Well as noted earlier the general contract title of the civil code is applicable to this case because of Articles 1676, 3131 and Art. 1675.
Definition
Art.1675
“A contract is an agreement whereby two or more persons as between themselves create, vary or extinguish obligations of a proprietary nature”.
Administrative contracts do share all of the above elements. The differences, however, extend beyond the requirements of Art. 1675 far in to the requirements of Art.3132 which partly reads as: “A contract shall be deemed to be an administrative contract where”
a) It is expressly qualified as such by the law or by the parties; or
b) It is connected with an activity of the public service and implies a permanent participation of the party contracting with the administrative authorities in the execution of such service.
Let us examine the elements of Art.3132: “Expressly qualified as such by the law or the parties”
According to this expression, a contract (remember Art.1675) will be an administrative contract if the law expressly qualifies it as an administrative contract. To this end, the law clearly enumerates what can be considered as administrative contract. But what if the law expressly disqualifies a contract to be an administrative contract? Both instances are the experiences of Ethiopia. Let us begin with the first. In the civil code we have such articles as Article 3207 and 3244 which expressly qualify contracts as administrative contracts. As to the second instance, we have the Mining Proclamation No.52/1993 which disqualifies contracts concluded by the administrative authorities with other parties under Art. 55(2).
The second implication of Art.3132 (1) is that parties may qualify expressly a contract as an administrative contract. An issue worth raising at this juncture will be ‘are all contracts administrative contracts merely because they are qualified as such by the parties? ’
Among other things, a contract qualified as such by the parties on face value cannot be considered as an administrative contract unless one of the parties is an administrative authority.
For one other reason to be consequently discussed i.e. for content consideration a contract merely qualified as an administrative contract by the parties will not also be an administrative contract. What about a contract that involves an administrative authority but not qualified as such by the parties? Stated otherwise are all contracts that make one of the parties an administrative authority administrative contracts? René David says
As a French legal scholar and as I think it fit, in our classification of law, public law should be distinguished from private law. Especially it is important to separate civil law from administrative law…contracts made by public officials have this [special trait] which enable us call them administrative contracts and treat them separately from civil law.[emphasis]
This, as it may, the civil code proceeds to say-“ … Connected with an activity of the public service and implies a permanent participation of the party contracting with the administrative authorities in the execution of such service”
The previous element is more or less concerned with the form of the contract, meaning the name the parties give to their contract when they first form it. The form it takes confers the contract a special nature.
Here we are concerned with the content of the contract, that is its object which determines the nature of the contract. Based on the object and the manner of meeting their object together with the type of the parties and their manner of participation in executing the object of the contract, we have another mechanism of distinguishing administrative contracts from ordinary contracts.
The object: this is one of the ways which is helpful to distinguish administrative contracts from the rest of the contracts. Art.3207 (1) identifies one of the objects as an activity of a public service”. In turn we have to consider what a public service is in our law.